County Buildings Under Construction
Community Center – Lee District – Workforce Development
Estimated Completion: Fall 2022
Funding: $3,000,000
Architect: Grimm & Parker Architects
Contractor: FHP Tectonics Corp.
Project Manager: Chris Lyon
Project Engineer: Luis Rosario
KEY FEATURES: This project entails the renovation of space to accommodate training opportunities in emerging technology fields, specialized equipment for skilled trades training, and job placement opportunities for residents.
Workhouse Buildings W13 and W15
Estimated Completion: Late 2022/ Early 2023
Funding: $6,300,000
Architect: Samaha
Contractor: Facilities Support Services
Project Manager: Eileen Gasteiger
Project Engineer: Wynton Lamb
KEY FEATURES: Renovation of the approximately 10,000 square feet in two historic buildings, W-13 and W-15, on the Workhouse Campus located at 9514 and 9517 Workhouse Way, Lorton VA for future tenant fit-out. Enhancements include both building plaza and Ox Road streetscape improvements.
Monument Drive Commuter Parking Garage and Transit Center
Estimated Completion: Fall 2023
Funding: $43,400,000 Funding has been provided by the VDOT I-66 Concessions funds.
Architect: HGA
Contractor: Howard Shockey & Sons, Inc.
Project Manager: Ipek Aktuglu
Project Engineer: Padam Sethi
KEY FEATURES: 820-space parking garage, 8-bus bay transit center with glass and steel canopy over the bus bays, a short-term parking area for pick up and drop off, commuter (slug) lanes, secure bicycle parking and storage, bicycle racks, solar panels to reduce energy consumption, and a partial green roof.
Springfield Community Business Center (CBC) Commuter Parking Garage
Estimated Completion: Fall 2023
Funding: $58,375,220 Funding is a combination of Federal, State, and County.
Architect: WDG
Contractor: Manhattan Construction
Project Manager: Jun Li
Project Engineer: Guoliang (David) Jiang
KEY FEATURES: 1100 parking spaces, pedestrian bridge across Old Keene Mill Road, 7 bus bay transit center, open air community use areas at grade and top deck, solar panels to reduce energy consumption, interesting exterior materials including metal fins, articulated precast, glass walls, and vegetated green walls.
South County Police Station and Animal Shelter
Scope: Construction of new 35,000 SF police station and 26,000 SF animal shelter at 8855 and 8875 Lorton Road, Lorton, VA
Estimated Completion: Spring 2023
Funding: $33,700,000
Architect: AECOM
Contractor: Forrester Construction Company
Project Manager: Tiffany Wilson
Project Engineer: Jyh-Mei Lee
KEY FEATURES: New police station and animal shelter for southern part of the County. Space for Animal Protection Police, community room, 20,000 SF outdoor space for animal shelter, fuel island to support fleet vehicles and associated parking, future solar (PV) system.
Edsall Road Fire Station
Scope: Renovation and expansion of existing fire station at 5317 Carolina Place Alexandria
Estimated Completion: Spring 2022
Funding: $9,000,000
Architect: Samaha
Contractor: Carlson Brothers Construction
Project Manager: Tiffany Wilson
Project Engineer: Keyan Kashefi
KEY FEATURES: Off site temporary fire station for Edsall Fire Station #26 replacement, four apparatus bays, site will be fully restored after use.
Police Heliport
Scope: Demolition of existing heliport and construction of replacement facility on existing site, 4604 West Ox Road, Fairfax, Virginia, including a 23,000 SF structure with helicopter landing area and maintenance bays, aircraft fuel station, offices, and site improvements.
Estimated Completion: Summer 2022
Funding: $13,000,000
Architect: Dewberry
Contractor: FHP Tectonics Corporation
Project Manager: Deepa Joshi
Project Engineer: Mais Al Mahamid
KEY FEATURES: Bay apron slope reduced to avoid slippery conditions, medical training room.
Lorton Community Center
Scope: Design and construction of a new Lorton Community Center, approximately 30,000 SF, located at 9520 Richmond Highway, Lorton Virginia.
Estimated Completion: Summer 2022
Funding: $18,500,000
Architect: Grimm + Parker Architects
Contractor: RJ Crowley
Project Manager: Martha Sansaver
Project Engineer: Karen Davis
KEY FEATURES: New one-story Community Center co-located with the Lorton Library with new playground and fitness areas, walking trails and outdoor recreation.
Lorton Community Library
Scope: Renovation and expansion of a the Lorton Community Library, approximately 16,000 SF, located at 9520 Richmond Highway, Lorton Virginia.
Estimated Completion: Summer 2022
Funding: $8,730,000
Architect: Grimm + Parker Architects
Contractor: RJ Crowley
Project Manager: Claudia Shalhoub
Project Engineer: Karen Davis
KEY FEATURES: Renovated and expanded existing Lorton Library co-located with the new Community Center with shared lobby space.
Reston Fire Station
Scope: Demolition of existing and construction of a new fire station located at 1820 Wiehle Avenue, Reston Virginia.
Estimated Completion: Late 2021
Funding: $12,200,000
Architect: Lemay Erickson Willcox Architects
Contractor: Branch Builds
Project Manager: Lisa A. Gossard
Project Engineer: Mais Al Mahamid
KEY FEATURES: Two story new replacement fire station building including four drive through apparatus bays.
Merrifield Fire Station
Scope: Renovation and minor addition of existing fire station located at 8739 Lee Highway, Fairfax.
Estimated Completion: Spring 2022
Funding: $9,000,000
Architect: Moseley Architects
Contractor: Sumter Contracting Corp.
Project Manager: James Sun
Project Engineer: Mohamed Abdel-Kariem
KEY FEATURES: One story freestanding building, three drive thru apparatus bays, fully renovated station.
Woodlawn Fire Station
Scope: Design and construction of a new 15,000 SF, four bay fire station located at 8701 Lukens Lane, Alexandria.
Estimated Completion: Summer 2022
Funding: $11,900,000
Architect: BKV Group
Contractor: Scheibel Construction
Project Manager: Maryam Mostamandi
Project Engineer: Timothy Danforth
KEY FEATURES: Two-story building with bunk rooms and an exercise room located over a kitchen, dayroom, and administration offices, attached to four drive thru apparatus bays
Lorton Volunteer Fire Station
Scope: Demolition of existing fire station and construction of new fire station with associated site improvements. The project also includes construction of temporary fire station.
Estimated Completion: Late 2021
Funding: $14,140,000
Architect: LeMay Erickson Willcox Architects
Contractor: Sorenson Gross Company
Project Manager: Claudia Shalhoub
Project Engineer: Padam Sethi
KEY FEATURES: Brick/stone veneer, high efficiency windows, insulated metal exterior doors, four apparatus bays
Liberty (Laurel Hill Adaptive Reuse)
Project Number: 2G08-001-000
Scope: An approximately 80 acre adaptive reuse project at the former Lorton Reformatory site.
Estimated Completion: Fall 2017 (Phase 1), Winter 2019 (Phase 2A), Summer 2021 (Phase 2B), and Summer 2022 (Phase 2C)
Funding: $12,765,000 County share of infrastructure project costs
Developers: The Alexander Company and Elm Street Development
Contractors: Southway Builders and William A. Hazel
Scope: A 2,100-space parking structure with bus bays, a Kiss & Ride and a pedestrian connection for Metro Silver Line-Phase 2. The County share of infrastructure needed to support the garage project are also included.
Estimated Completion: The project has been completed and is anticipating the Metro station opening.
Funding: $52 Million
Architect: Hammel, Green and Abrahamson
Contractor: Manhattan Construction
Construction Manager: Mohammed Abdel-Kariem
Project Coordinator: Gasim Elfaki
Sully Community Center
Scope: Design and construction of a new Sully Community Center, approximately 32,000 SF, located at 13800 Wall road, Herndon Virginia.
Estimated Completion: Spring 2022
Funding: $21,900,000
Architect: RRMM Lukmire Architects
Contractor: Henley Construction
Project Manager: Jun Li
Project Engineer: Si Ghiwane
KEY FEATURES: One story new multi-generation community center with double gym and a health care suite.